Study EVM (Earned Value Management) – 2
Once the CPI/SPI were calculated at some time-stamp, project manager should be deeper analyses, he need to predict the future cost: ETC (Estimate To Completion) Then EAC (Estimate At Completion) = AC +...
View ArticleStudy EVM (Earned Value Management) – 1
During the past few days I was studying Project Time Management in PMBOK, for preparing the upcoming PMP exam on 4th December 2010, while I spent a few hours on understanding/mastering EVM, I log my...
View Article